In Türkiye, under Article 21 of Zoning Law No. 3194, a building permit from the municipality or governorship is required to construct a new building, with certain exceptions. The permit is issued on the owner's application, with architectural, structural, electrical and mechanical drawings prepared in line with the zoning status. As a rule, changes to a permitted building also require a new permit (Zoning Law No. 3194).
Before the permit: zoning status
Everything starts with the plot's zoning status. The zoning status document shows how much can be built on the plot (floor area ratio, footprint), building height, setbacks and permitted use. The architectural design is drawn within these limits. The calculation rules are defined in the Planned Areas Zoning Regulation; we explain the details in our villa project guide.
Which documents are needed for a building permit?
Under Article 22 of the Zoning Law, the application is made by petition by the owner or their legal representative, with the following attached:
- Title deed (in exceptional cases, a document replacing the title deed)
- Architectural drawings
- Structural (reinforced concrete / steel) drawings
- Electrical and mechanical drawings, plans and calculations
- Site plan with reference points (or a dimensioned site sketch)
In practice, municipalities also ask for additional documents such as a soil survey, a building inspection contract, approvals from the relevant professional chambers and an energy performance calculation. The current list should be confirmed with the municipality responsible for the plot (for example, Eyüpsultan Municipality for Göktürk and Kemerburgaz).
How long does a permit take?
Under the law, the municipality or governorship reviews the application and, if nothing is missing or wrong, issues the permit within 30 days of the application at the latest. If something is missing or wrong, it notifies the applicant in writing within 15 days; once corrected, the permit is issued within 15 days of the new application at the latest (Zoning Law Art. 22). Design preparation and approval processes fall outside these legal periods, so allow separately for the design stage when setting the schedule.

Which work needs no permit?
Under Article 21 of the law, pointing, internal and external plaster, paint, whitewash, gutters, windows and doors, floor and ceiling finishes, electrical and plumbing repairs, roof repair and relaying tiles, and other alterations and repairs that do not affect structural elements are not subject to a permit. Any intervention that touches the structure needs separate assessment; we explain this in our article on structure and permits.
What is an occupancy permit (iskân)?
When the building is completed, an occupancy permit must be obtained from the authority that issued the building permit before it can be used. The authority checks that the building complies with the permit and its attachments and is technically safe to use, and must conclude the application within 30 days at the latest (Zoning Law Art. 30). The occupancy permit is needed to make electricity, water and gas subscriptions permanent and to move to condominium ownership on the title deed.
Where are applications tracked?
Permit and occupancy procedures are largely run through municipalities' electronic systems and the e-Government services of the Ministry of Environment, Urbanisation and Climate Change (e-Government Gateway). Owners are advised to follow the process step by step together with the architect who prepared the drawings.
“A permit is not a formality; it is proof that the building is safe and legal.”
Conclusion
The building permit process runs smoothly with a correct reading of the zoning status and complete drawings. We prepare architectural designs according to zoning conditions and accompany owners through the permit process. For details see our architecture service and our article on design stages. This article is for general information; as legislation can change, confirm current conditions with the relevant municipality.
Frequently asked questions
How many days does a building permit take in Türkiye?
Under the Zoning Law, a complete application must be concluded within 30 days at the latest. If something is missing, this is notified within 15 days, and the permit is issued within 15 days at the latest after it is corrected. Design preparation is outside this period.
Which drawings are needed for a permit?
Architectural, structural, electrical and mechanical drawings and their calculations. Municipalities also ask for additional documents such as a soil survey and a building inspection contract.
Do paint and kitchen renewal need a permit?
No. Under the Zoning Law, work that does not affect structural elements, such as paint, plaster, windows, floor and ceiling finishes and service repairs, is not subject to a permit.
Can you move in without an occupancy permit?
Under the law, an occupancy permit is required before a building can be used. It is also needed for permanent utility subscriptions and condominium ownership.
From the Journal
All articles →- Architecture

· 3 min read
Garden and landscape design: making a villa's outdoor space part of the home
Terrace, decking, pool surround, planting, irrigation and night lighting: how to design the garden as a second layer of the home's architecture.
- Architecture

· 3 min read
Energy-efficient homes in Türkiye: insulation, windows, heating and the Energy Performance Certificate
What is the Energy Performance Certificate (EKB) and what is it for? How to reduce a home's energy demand through design, including the 2026 regulation change.
- Architecture

· 3 min read
Villa facade design: exterior cladding materials and how to choose
Stone, wood, render, composite and glass: material choice for a villa facade, its relationship with insulation, maintenance needs and the effect of climate.